| ===== 8. Conclusions ===== | ===== 8. Conclusions ===== | ||
| - | ==== Achievements ==== | + | |
| - | //Discuss here what was achieved | + | ==== 8.1 Achievements ==== |
| - | ==== Limitations ==== | + | |
| - | //Identify here the limitations of the solution and prototype.// | + | The Connect project set out to transform a standard metro carriage into a participatory space that counteracts digital isolation through ambient light interaction and asynchronous voice exchange. Evaluated against the four objectives defined in Section 1.4, all primary targets were met. |
| - | ==== Future Development ==== | + | |
| - | //Provide here your recommendations | + | The functional core of the system |
| + | |||
| + | All performance targets were met. End-to-end latency from sensor contact to LED illumination was confirmed below 100 ms. No ghost triggers were observed during electromagnetic interference testing with a brushed DC motor operating in proximity to the CAN wiring. Enclosure surface temperature remained below 50 °C after four hours of continuous operation at 80 % LED brightness, end-of-line voltage remained above 4.7 V under full white load, and the system retained full electrical sensitivity after 1000 automated trigger cycles. | ||
| + | |||
| + | Structural and safety validation was completed. Finite Element Analysis of both the ceiling-mounted main box and the pole-mounted secondary node confirmed safety factors exceeding 12.0 and 30.0 respectively against the yield strength of Nanovia PA Rail. Electrical continuity between enclosure and ground was confirmed below 0.1 Ω, all cable and filament materials carry V-0 or LSHF certification, | ||
| + | |||
| + | Software testing passed in full. CAD integration confirmed zero mechanical interference between components with the required 5 mm clearance maintained. CAN bus arbitration correctly prioritised the higher-priority node ID under forced collision conditions. The animation algorithm ran for 24 hours in simulation without memory leaks or buffer overflows. Heartbeat timeout detection triggered within 500 ms of CAN disconnection and correctly switched the LED output to static safety white. | ||
| + | |||
| + | The web platform reached a deployable state. Load testing at 1000 concurrent requests produced a zero error rate and a mean latency of 195.77 ms on the write endpoint. The System Usability Scale evaluation returned a mean score of 86.59 across 11 participants, | ||
| + | |||
| + | The prototype was delivered within the 100 € budget constraint at a total cost of 97.92 €. | ||
| + | |||
| + | ==== 8.2 Limitations ==== | ||
| + | |||
| + | The prototype represents a deliberate functional reduction and several gaps between | ||
| + | |||
| + | The prototype covers a single handrail segment with two nodes. The full designed | ||
| + | |||
| + | Fire-rated enclosures were not fabricated for the prototype. | ||
| + | |||
| + | The dual-rail power architecture was not implemented. The prototype uses a single 5 V bench supply in place of the six step-down converters and dual 12 V and 5 V distribution chain specified for the full installation. Behaviour of the power architecture under worst-case current draw across all eleven nodes has not been empirically verified. | ||
| + | |||
| + | Phase 2 was not evaluated in a simulated transit environment. The QR voice messaging platform was assessed via load testing and SUS scoring, but end-to-end passenger behaviour, including QR code discovery at exit doors and the intentional delay mechanic, was not observed under realistic boarding and alighting conditions. | ||
| + | |||
| + | ==== 8.3 Future Development ==== | ||
| + | |||
| + | Scaling from two nodes to the full eleven-node network is the primary technical extension. This requires fabrication of additional Sensor Node PCBs and validation of bus arbitration timing under simultaneous transmission from multiple nodes. The heartbeat timeout and safety-white fallback logic should also be confirmed correct when any single node drops from a live eleven-node network. | ||
| + | |||
| + | Enclosure fabrication in Nanovia PA Rail is required before any deployment in a transit environment. A Portuguese or EU-based supplier should be identified to reduce logistics cost and lead time at scale. The enclosure geometry is defined and FEA-validated; | ||
| + | |||
| + | The dual power rail should be implemented and verified with converters sized for worst-case current draw across the full node count. Voltage drop along the LED strip should be re-confirmed against the 4.7 V minimum under the full three-strip, | ||
| + | |||
| + | For Phase 2, a pilot deployment in a controlled transit-adjacent environment, | ||
| + | |||
| + | The heart rate sensing capability referenced in Section 1.5.3 and the auditory feedback output described in Section 1.4 were not implemented in this iteration. Both represent additional sensing and output channels that would enrich the interaction model and bring the system closer to the full vision outlined in the initial objectives. | ||