| The whole report have been standardized (same format on all headings, introductions, | The whole report have been standardized (same format on all headings, introductions, | ||
| + | |||
| + | ==== 10th Week Report ==== | ||
| + | 18.05-24.05\\ | ||
| + | **Prototype** | ||
| + | * the assembly of prototype was a bit blocked this week because of missing materials | ||
| + | * designs for the prototype was made | ||
| + | **Communication materials** | ||
| + | * all communication materials was updated: leaflet, poster, packaging poster | ||
| + | **Paper** | ||
| + | * Paper got feedback and was fixed according to that | ||
| + | * everyone wrote personal sentences for the paper | ||
| + | **Webapp** | ||
| + | * the webapp had some adjustments with prompts in send and read page | ||
| + | * testing of API was made and was ok | ||
| + | |||
| + | ==== 11th Week Report 25.05-31.05 ==== | ||
| + | |||
| + | * The assembling of the prototype have been started | ||
| + | * Stress analysis added to the report | ||
| + | * Scientific paper first sections are done. Now the more technical parts is missing and need to be prioritized | ||
| + | * The group has started the work to prepare for the final presentation by making the pre-presentation for monday 1st | ||
| + | |||
| + | ==== 12th Week Report 01.06-07.06 ==== | ||
| + | |||
| + | **Project management** | ||
| + | * Retrospectives added to the report and sprint outcomes almost done | ||
| + | |||
| + | **Tests and results** | ||
| + | * tests of the prototype was conducted and added to report | ||
| + | |||
| + | **Other** | ||
| + | * drawing of two people was the 3D design of the metro carriage | ||
| + | * the scientific paper was finalized and delivered | ||
| + | * Content for video was made, ready to be clipped/ | ||
| ===== Meetings ===== | ===== Meetings ===== | ||
| Line 452: | Line 486: | ||
| * software testing was fine without remarks | * software testing was fine without remarks | ||
| * Benedita and Rui made a plan for getting materials for prototypes | * Benedita and Rui made a plan for getting materials for prototypes | ||
| - | ===== Activities ===== | ||
| - | //Please register here all accomplished project activities// | ||
| - | ^ Start ^ End ^ Task ^Description ^ Who^ | + | |
| - | | | + | ==== 10th Meeting (2026-05-28) ==== |
| - | | | | | + | |
| + | [[https:// | ||
| + | ===Agenda=== | ||
| + | * Review of paper so far | ||
| + | * Review of prototype assembly so far | ||
| + | ===Minute=== | ||
| + | |||
| + | **Prototype** | ||
| + | * Jorge need to see and revise stress analysis in both report and paper. Make sure files that are sent to him is stp format | ||
| + | * All components are here now for the prototype: it needs to be printed but the material is here | ||
| + | |||
| + | **Paper** | ||
| + | * complete citing nr. 14 | ||
| + | | ||
| + | * finalize paper next week | ||
| + | * what is red needs to be fixes. what is blue Benedita already fixed | ||
| + | |||
| + | ==== 11th Meeting (2026-06-03) ==== | ||
| + | |||
| + | [[https:// | ||
| + | ===Agenda=== | ||
| + | * Review of paper: do we delete the rest of the «LaTex help text» and the citations that was added from before? | ||
| + | * Review of prototype assembly so far | ||
| + | * Review 3D model for prototype | ||
| + | ===Minute=== | ||
| + | |||
| + | **Video**\\ | ||
| + | The promotional video should be free-format and will be used at the conference. Suggested structure: introduce ourselves, problem, solution, how we accomplished it (2–3 min). Some teams use the video to share personal experiences, | ||
| + | **Presentation**\\ | ||
| + | Nothing should be read from paper or phone during the presentation. The auditorium is available on Monday 15 June for rehearsal. The start page of the presentation should define the project requirements — to be checked whether this has already been done. The link to today' | ||
| + | **Scientific Paper (deadline: 5 June)**\\ | ||
| + | * Add a silhouette of one or two people to the figure in Section 3.1; include ceiling view if possible. Same images to be added to the report. | ||
| + | * Remove the paragraph/ | ||
| + | * Remove all remaining help/ | ||
| + | * Benedita will add notes and citations directly | ||
| + | |||
| + | |||
| + | ==== 12th Meeting (2026-06-11) ==== | ||
| + | |||
| + | [[https:// | ||
| + | * Review of prototype | ||
| + | * Review test/ | ||
| + | * final deliverables | ||
| + | |||
| + | ===Minute=== | ||
| + | |||
| + | **Project management**\\ | ||
| + | Important that this is done and finished so the teacher will have time to give a grade. Send email to teacher when it is finished. | ||
| + | |||
| + | **Test & results**\\ | ||
| + | We went through what tests passed and not and possible explanations to why. Benedita was pleased to se the prototype so far | ||
| + | |||
| + | **25th** | ||
| + | * We need to print the poster and leaflet/ | ||
| + | * A table for each team for the prototype | ||
| + | * Space for poster in A3 | ||
| + | * Everyone will cook/bring something | ||
| + | |||
| + | **Other**\\ | ||
| + | Benedita - we go to her office in the afternoon to get more materials for the prototype | ||